- SAP PM Tutorial
- SAP PM - Home
- SAP PM - Overview
- SAP PM - Technical Objects
- SAP PM - Equipment Master Record
- Functions of Technical Objects
- SAP PM - Creating Multilingual Text
- SAP PM - Breakdown Maintenance
- SAP PM - Corrective Maintenance
- SAP PM - Creating/Planning MO
- SAP PM - Preventive Maintenance
- SAP PM - Maintenance Planning
- Project Oriented Maintenance
- SAP PM - Refurbishment Process
- SAP PM - Warranty Claim Processing
- Mobile Applications For EAM
- Work Clearance Management
- SAP PM - Information System
- Cross Application Time Sheet
- SAP PM - Single & Composite Roles
- SAP PM Useful Resources
- SAP PM - Questions Answers
- SAP PM - Quick Guide
- SAP PM - Useful Resources
- SAP PM - Discussion
- Selected Reading
- UPSC IAS Exams Notes
- Developer's Best Practices
- Questions and Answers
- Effective Resume Writing
- HR Interview Questions
- Computer Glossary
- Who is Who
SAP PM Online Quiz
Following quiz provides Multiple Choice Questions (MCQs) related to SAP PM. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.
Q 1 - In Plant Maintenance, arrange the following tasks in correct order?
Notification
Newly Created Work Order
Creation of Purchase request for work orders
Purchase Order created and parts Received
Parts issues to Work Order
Approval and Planning of Work Order
Answer : D
Explanation
Key Steps that are included as part of Work Order Notification under SAP PM −
- Notification
- Newly Created Work Order
- Creation of Purchase request for work orders
- Purchase Order created and parts Received
- Parts issues to Work Order
- Approval and Planning of Work Order
- Scheduling and Releasing Work Order
- Work Order Execution
- Closing a Work Order
Q 2 - Which of the following is incorrect about Breakdown maintenance?
A - Equipment is not working properly.
B - Production is effected when a technical equipment went breakdown.
C - There is a malfunction occurs for any of the equipment.
Answer : D
Explanation
In Breakdown maintenance, you create a M2 malfunction notification and PM02 order type and equipment is repaired at the site.
Q 3 - Which of the following plan can be created without a maintenance strategy and is used for performance based maintenance?
Answer : C
Explanation
A multiple counter plan can be created without a maintenance strategy and is used for performance based maintenance. In the multiple counter plan you create maintenance cycles and allocate counters of equipment or functional locations with different dimensions to them.
Q 4 - Which of the following submodule of Plant Maintenance is used to control and monitor the safety measures?
Answer : C
Explanation
Work Clearance Management in Plant Maintenance is used to control and monitor the safety measures. It provides safe working conditions for employees in the organization and to follow the environmental protection regulations.
Q 5 - In SAP Plant Maintenance, Refurbishment process is integrated with MM, CP and PS?
Answer : A
Q 6 - Which of the following feature helps field service technicians to access all the work related information on their mobile devices?
A - Mobile Applications for EAM
Answer : A
Q 7 - Which of the following is not a type of maintenance plan?
Answer : C
Q 8 - Which of the time based scheduling allows you to perform Maintenance strategy every 30 working days?
Answer : C
Explanation
Time-based (for example, every 30 days)
Time-based by key date (for example, every 30 days on the 30th day of the month)
Time-based by factory calendar (for example, every 30 working days)
Q 9 - When you create a maintenance strategy plan for a Printer to be performed after 1 million copies, it is example of?
Answer : B
Q 10 - A Repair is known as- all measures which restore the ideal condition of a technical system?