- SAP SCM Tutorial
- SAP SCM - Home
- SAP SCM - Overview
- SAP SCM - Components
- SAP SCM - Benefits
- SAP SCM - Demand Management
- SAP SCM - Creating PIR
- Material Requirement Planning
- SAP SCM - Planned Order Creation
- Production Order Creation
- SAP SCM - Goods Issue
- Production Order Confirmation
- Production Order Cancellation
- SAP SCM - Integration
- SAP SCM - Integration Models
- SAP SCM - Master Data
- SAP SCM - Resources
- Production Data Structures
- Transfer Changed Master Data
- SAP SCM - Transfer Changed BOMs
- SAP SCM - Models and Versions
- SAP SCM - Applications
- Advanced Planning Optimization
- SAP SCM - Extended Warehouse
- Transportation Management
- Supply Network Collaboration
- Forecasting & Replenishment
- Consultant Responsibilities
- SAP SCM Useful Resources
- SAP SCM - Questions Answers
- SAP SCM - Quick Guide
- SAP SCM - Useful Resources
- SAP SCM - Discussion
- Selected Reading
- UPSC IAS Exams Notes
- Developer's Best Practices
- Questions and Answers
- Effective Resume Writing
- HR Interview Questions
- Computer Glossary
- Who is Who
SAP SCM Mock Test
This section presents you various set of Mock Tests related to SAP SCM. You can download these sample mock tests at your local machine and solve offline at your convenience. Every mock test is supplied with a mock test key to let you verify the final score and grade yourself.
SAP SCM Mock Test I
Q 1 - Which of the following module deals with activities associated in transformation of goods from raw material, movement of goods to end users and information work flows?
Answer : B
Answer : D
Explanation
SAP Supply Chain Management is one of the key module in SAP ERP and controls Production Planning, business forecasting and demand planning, and helps the organization to manage their supply chain process in a dynamic environment.
Q 3 - Which of the following is not a key attribute of Supply Chain Management process?
Answer : D
Q 4 - Which of the following application is not part of Supply Chain Management process?
A - SAP Supply Network Collaboration SNC
B - SAP Extended Warehouse Management EWM
C - Advanced Planning and Optimization (APO)
Answer : D
Explanation
The primary applications are SAP General Areas, SAP Supply Network Collaboration SNC, SAP Extended Warehouse Management EWM, Advanced Planning and Optimization (APO), Forecasting and Replenishment FRE and SAP Transportation Management TM.
Q 5 - In which of planning strategy, stock is produced without sales order and is used to meet customer demands in future?
A - Make to Stock Planning strategy
Answer : A
Explanation
Make to Stock Planning strategy (MTS) −
This is planning strategy where stock is produced without sales order. It is used to meet customer demands in future.
Q 6 - In MTO planning strategy, finish products are not produced until you receive sales order from a customer?
Answer : A
Q 7 - When you use Planning strategy 10, which of the following is correct?
A - Only PIR quantity is considered for MRP run & PIR requirement type is VSF.
B - Sales order are completely ignored.
C - For MRP run maximum of 2 PIR and Sales order can be considered
Answer : A
Explanation
When you use Planning strategy 10, only PIR quantity is considered for MRP run and sales order are completely ignored. In this PIR requirement type LSF and is reduced when you deliver stock to customer.
Q 8 - Functions related to Supply Chain management in SAP ERP system are all of the following except?
Answer : D
Explanation
SC Collaboration −
This is used to help in making collaborative forecasts and agreements.
SC Planning −
This is used to generate the operational plans as per current and relevant data in the system.
SC coordination −
This component in Supply Chain is used to coordinate the exchange of data and information between different business units.
SC Execution −
This is used to ensure that you execute the supply chain plans in the best possible manner to get the desired result.
Q 9 - In a manufacturing enterprise, which of the following is not a part of Internal Supply chain management?
Answer : C
Q 10 - Which of the following movement type is used for Goods Receipt in to Warehouse?
Answer : A
Q 11 - In SCM, which of the following process deals with demand planning to link to Customer Relationship Management CRM to get data related to customer campaigns?
Answer : A
Explanation
Forecasting −
To perform demand planning and forecasting, you can link to Customer Relationship Management CRM to get data related to customer campaigns, etc.
Supply Network Planning SNP −
To view organization as a network of locations and to check stock projections and stock keeping criteria. Calculations in SNP drive dependent requirements down to supplying locations production and receiving stores.
Production Planning and Detailed Scheduling −
This is to check the dependent requirements from locations within the supply network, passed down from SNP.
This is linked with Material Requirement Planning MRP in Production Planning, which determines the inbound material required to complete a production order.
Q 12 - Which of the following is/are benefits of Supply Chain Management process?
B - To effectively manage forecasting and handling sudden changes in demand and supply process.
C - To effectively use Net Fixed assets NFA like plants and equipment.
Answer : E
Answer Sheet
Question Number | Answer Key |
---|---|
1 | B |
2 | D |
3 | D |
4 | D |
5 | A |
6 | A |
7 | A |
8 | D |
9 | C |
10 | A |
11 | A |
12 | E |